Knowledge
JEM has the technology and knowledge cultivated over many years of experience.
Here we introduce some of the know-how we have accumulated through our actual onsite activities.
Knowledge illustration list
There is spring water in the upward PS anchor hole of the arch section!
Know-how for slope cutting work on surge tanks.
Upward PS anchor drilling RPD machine.
Structure of the PS anchor (nut type) at the mouth.
Upward drilling of PS anchors.
What is the grout that stopped the tunnel sidewall extrusion?
Construction of tunnel inverts.
What is above the underground power station?
Types of ground reinforcement grout.
Strata and groundwater in the cable shaft.
Various shapes of underground power station cavities.
Concrete placement for the arch section lining of the underground power station cavity.
Knowledge list
Heading
- Six Methods for Groundwater Control in Shaft Excavation
- Verification Items During PS Anchor Testing
- Technical Inheritance and Digitization for Large-scale Excavation
- Strength Specifications for Shotcrete on Slopes
- Grouting for Groundwater Treatment in Upward PS Anchor Holes in Underground Power Plants Arches
- Standards for Groundwater Treatment in PS Anchor Holes in Underground Power Plants Arches and Water Stopping
- Measures to Improve PS Anchor Cycle Time
- Causes of Variability in Load Measurement Values of PS Anchor Load Cells
- Encountered Expansive Mudstone Geology During Tunnel Construction
- Planned Layout for Underground Power Plant Work Shafts in Mudstone Geology
- Historical Changes in Japan's Underground Power Plants
- Rain Measures Unique to Tropical Rainforests
- Curtain Grouting Above the Underground Power Plant Cavern
- Tunnels Using NATM Method
- The underground cavities excavated for power plants in mudstone geology.
- Upward Drilling and Insertion of PS Anchors
- Management Values for Elongation During PS Anchor Tensioning
- Points to Note During Manufacturing of Covering formwork of Large sectional Arch Lining Concrete
- Fundamental Technologies for Underground Power Plant Cavern Construction
- Rapid-setting Materials for Shotcrete
- Shaft Winch Repairs Completed After an Accident
- Concrete Placement for Water Pressure Steel Pipe Shafts
- Special High-altitude Work Vehicles Used at Underground Storage Base Sites
- Standards for Concrete Placement in Arch Linings for Underground Power Plants
- Basic Review of Changed Underground Power Plants Construction Plans
- Vibration Control from Blasting at PS Anchor Anchorage Sections
- Causes of Increasing Load Cell Values of Upward PS Anchors in the Arch Sections of Underground Power Plants
- Safety Factors Used in Underground Power Plants Cavern Design
- Management Standards for Excavation in Underground Power Plants Arches
- Rock Support for Large-section Underground Power Plant Arches
- Management Standards for Wire Elongation During PS Anchor Tensioning
- Analysis of Underground Cavities
- Filling of Over Cutting Tunnels
- Blasting for Invert of Large-section Tunnels
- Drilling Diameter for Rock Bolts and Method of Grouting
- Downward Installation Angle of Sidewall Rock Bolts and Mortar Filling Behind Washers
- Concrete for Large-section Diversion Tunnel Linings
- Displacement Measurement Associated with Tunnel Excavation
- Days Required for Arch Lining Work in Underground Power Plant Caverns
- Installation of Upward Rock Bolts
- Measures to Prevent Fall of rocks at Tunnel Faces
- Evacuation During Tunnel Blasting
- Form Removal Time and Concrete Strength for Large-section Tunnel Arch Concrete
- Preparation of Construction Plans for Large-section Diversion Tunnel Linings
- Details of Covering formwork for Large-section Tunnel Arch Lining
- Concrete Placement for Large-section Tunnel Arches
- Reinforcement Assembly for Large-section Tunnel Arches
- Pre-investigation and Displacement Measurement Plan Before Starting Underground Power Plant Caverns
- Management Standards for Elongation Values During Tensioning of PS Anchors in Underground Arch Sections
- Geothermal Measurement Inside Tunnels
- Differences Between Load Cell Indications and Tension Jack Readings for PS Anchors
- Installation of Underground Displacement Gauges
- Investigation of a 100-year-old Power Plant Waterway Tunnel
- Cutting Slope Protection Works at Tunnel Inlets
- Groundwater Amounts Feasible for Shaft Excavation and Sheet Piling for Shafts
- Construction Considerations for Water Conveyance Tunnels and Water Pressure Pipe Shafts
- Secondary Grouting Below PS Anchor Packers
- Grouting Construction Plan for Power Plant Waterway Tunnels
- Turbidity Treatment Facilities for Power Plant Construction and Tunnel Inlet Construction and Slope Cutting
- Lahar Layer Water Pumping and Pump Test Inside Shafts
- Measurement Management Plan for Large-section Tunnels in Shirasu Soil
- Preparations Before PS Anchor Installation
- Verification After Completion of PS Anchors in the Underground Arch of the Power Plant